Operation Restore progress update as at 2010-02-22

By Dave Gale on Monday 22nd of February 2010 12:00 AM


By this morning, Monday 22 February 2010, 70% of the Gauteng schools have been migrated to G11.  The sites we are now dealing with are those where civil engineering work is needed to reposition the dishes, and where technical or logistical challenges have thwarted us so far.  We still aim to have as close to 100% of the schools up by the end of February.

The migration of our Western Cape customers started over the weekend, after installation teams had been trained on the new equipment we are using.  These sites should also be migrated by the end of the month.

To date, we have been frustrated with logistical challenges, especially with timely supply of new equipment. As most of these issues had been ironed by this morning, we're optimistic that apart from sites which have specific technical challenges, the repointing  should proceed without further delays.

 